Tuesday, 22 May 2012

Hebel Hurrah

The first sheets of Hebel were installed today.
The sheets are heavy and have to be manually carried to there position on the site. If Metricon hadn't insisted on a fence it would have been much easier for the installers, the delivery truck could have distributed around the site. Each panel weighs approx 100kg.
The full panels go in easy, cutting is a slow process.

The back side of the house has most of its full sheets installed.
Back of house

Master Bedroom and En Suite



The plasterers continued. A few areas are done in square set, but mostly cornices.

Entrance all done in square set.

Kitchen
Problems encountered with the council and the septic dispersion trenches. Council have advised we must move the fill from the site cut out of the area. Big and costly exercise, will probably have to move the fill off site as we have no where to spread it with easy access.

No comments:

Post a Comment